Water system improvements

Contract #3 – Old Rome State Road water main

  • January-June 2024 – Design plans and specs
  • September 2024 – Submit to Jefferson County
  • December 2024-January 2025 – Agency approval
    • Received comments from NYSDOH (11/5/24)
    • B&L addressing and providing response
  • Spring 2025 – Bidding
  • Spring-Summer 2025 – Construction

Water meter replacements

  • January 2024 – Core & Main contract award
  • March-June 2024 – Antenna installation
  • Ongoing – Meter replacements by Town staff
    • <10 left to replace
  • Ongoing – Billing integration
    • Core & Main to schedule training session