Customers in Water District #1, specifically in the Paddy Hill area, may experience low water pressure until further notice. This temporary reduction is necessary while the old Brownville Bridge is being demolished and is intended to prevent excess pressure from building up in the water lines.

Zoning Fees have been amended with the additional penalty fee for work/use started before obtaining the required zoning permit. The fee will be $200.

Sewer District #1

Completed

  • December 2023 – Plans delivered to NYSDOT
  • January 2024 – NYSDEC submission
  • July 2024 – Inter-Municipal agreement (IMA) with Brownville
  • July 2024 – WIIA Grant submitted
  • August 2024 – EDA Grant application
  • July-November 2024 – NYSDEC and NYSDOT approval
  • December 2024 – Additional comments received from NYSDEC
    • B&L providing responses
    • Scheduling meeting with Brownville for NYSDEC requested acceptance letter

Next Steps

  • Ongoing – Easement coordination
    • January 2024 – Meeting with remaining property owners
    • County easements expected within the next month
  • Winter 2024 – Bidding
  • Spring-Summer 2025 – Construction

 

*****Once complete, this infrastructure will serve the Watertown International Airport only*****